Construction of R1 Bahmut Bypass

Stronger economy
5,325,090.37 Euro
SOE State Road Administration
2017 - 2019
Ongoing
Bahmut Bypass runs from km 68+250 to km 74+177 of r1 Chisinau-Sculeni Road. The construction is a new alignment for a length of about 5.9 km running south of and parallel to the existing road and close to the existing railway line.

Results:

 

The new construction will be a 2-lane road of a 3.50 m lane width and shoulders of 2.50 m width on each side, an underpass for pedestrians, numerous culvert and three road junctions.

The progress of Works is estimated at 9,3%.

The Contractor during the month September 2019 has continued with the construction of the pipe and box culvert.

The Contractor has identified a borrow pit for fill in Cornesti and km 74+000 on the left-hand side. During the month June 2019 there was a problem with the permit and license to operate borrow pit and the Contractor has been stopped from taking material from this borrow pit until the permit and license has been renewed. The Contractor would provide to the Employer and Engineer for the cost obtaining fill material from another offsite location

 

Contact details:

Engineer-Rendel Limited- Mr. John Wyatt, Engineer’s Representative/Team Leader j.wyatt@rendel-ltd.com

Contractor-Rutador S.R.L.- Mr. Claudio VOLPE, Contractor’s Representative info@rutador.md

Employer-S.E. “STATE ROAD ADMINISTRATION”- contracts.administration@asd.md

 

 